top of page
Projects Banner.png

Haiti - Hospital Rehabilitation and Activation

€3.5m | 2.5 years | ~100 personnel | 6 contractors

​

Challenge
Transitioning temporary medical services into a permanent 68-bed hospital facility amid insecurity, changing operational requirements and significant coordination demands.

​

Role
Senior operational/project leadership across the medical and construction programmes.

​

Delivery
CEmONC, operating theatres, maternity infrastructure, neonatology, supporting infrastructure.

​

Outcome
Transition from temporary to permanent service delivery.

MIJ Post-op.png

DRC - Emergency and Ebola Infrastructure

€120k | 6 months | 3 facilities | Remote deployment

​

Challenge
Delivering emergency isolation capacity rapidly during an Ebola response while working in remote locations and an environment of severely strained community trust.

​

Role
Infrastructure and logistics management from planning and conception through design, procurement, construction and activation.

​

Delivery
Durable emergency ward, four-room Ebola isolation facility and a separate rapid-deployment isolation centre in a remote location.

​

Outcome
Delivered two durable facilities and a separate rapid-deployment isolation facility, combining immediate emergency capacity with longer-term infrastructure value and community acceptance.

DRC 1.png

CAR - Health Centre Construction

€6m annual programme | 200 staff | 300 MoH staff | Multiple facilities

​

Challenge
Delivering new and rehabilitated health infrastructure while maintaining a major regional health operation across multiple locations.

​

Role
Project management across infrastructure delivery, health services and government engagement.

​

Delivery
New health centres in Boya and Ngakobo, and rehabilitation of the Sido health post.

​

Outcome
Delivered multiple infrastructure projects while maintaining continuity of a major regional health operation.

Ngakobo - 1 Final.png

Sudan - Hospital Conception and Construction

€1m | 3 months initial assignment | ~35 inpatient beds | 15-bed maternity unit

​

Challenge
Developing secondary-care capacity rapidly for refugees in a setting with limited infrastructure, changing requirements and difficult ground conditions.

​

Role
Construction management from hospital concept and design through mobilisation and construction.

​

Delivery
Hospital concept development, design coordination, site preparation, procurement, contractor mobilisation and management.

​

Outcome
Moved the project from concept and design into active construction, with major groundworks initiated during the initial three-month assignment.

Teneidba 1.jpeg

DRC - COVID Treatment Centre

€50k | 3 weeks | 10 staff | 4 contractors
 

Challenge
Rapidly rising COVID-19 cases required adapting an existing Ebola treatment centre.

​

Role
Logistics and infrastructure management, coordinating construction delivery and activation.

​

Delivery
Assessed and redesigned the existing facility, planned adaptations, managed procurement and mobilisation, coordinated four contractors, and integrated infrastructure works with medical requirements.

​

Outcome
Converted an existing Ebola facility into a COVID-19 response facility in approximately three weeks.

COVID treatement centre.png

Syria - Health Infrastructure Rehabilitation & Diagnostic Capacity

€390k | 7 months | 2 concurrent programmes | Multiple facilities

​

Challenge
Develop and rehabilitate health infrastructure in highly restricted operating environments while coordinating multiple projects.

​

Role
Logistics and infrastructure management across two concurrent health programmes.

​

Delivery
Clinic rehabilitation, modular laboratory and X-ray facilities, contractor coordination and sequencing of concurrent works.

​

Outcome
Delivered rehabilitated health facilities alongside new modular diagnostic and laboratory capacity.

Image Coming Soon.png
bottom of page